Commissioning of 3 STS cranes at King Abdulla Port, Saudi Arabia
Started Date | 3rd January 2015 |
Current Status | Completed |
Brief Description of service |
3 STS cranes were commissioned by ZPMC Lanka employees and following was carried out during the commission project · Removing sea fasteners and offloading of all the cranes during and heavy windy period to the port under construction. · Make the 11kv electrical connection for the QCs. · Complete all the pending requirements of the equipment. · Commissioning and testing · Equipment handover.
|
Manpower Strength |
· 1 Qualified and well experienced electrical engineers and assistant electrical engineer. · 6 Experienced Mechanical Technicians · 2 Experienced Electrical Technicians
|