Modification of a discharge pipe of a dredger belongs to CCCC Guangzhou Dredging Co., LID
Started Date |
2nd March 2015
|
Current Status | Completed |
Brief Description of service |
· Fabrication of a 850mm diameter & 16mm thick, “y” shaped pipe section as per the drawings. · Modify the available flanges according to the requirement. · Adjusting the pre – fabricated “Y” shaped pipe section according to the dredger available configurations. (Due to mismatch of the drawing & available pipes.) · Welding and fixing the pipe with flanges. · Complete minor repairs in the dredger. |
Manpower Strength |
· 4 Qualified welder & Fabricators · 3 Mechanical Technicians · 1 Qualified Mechanical Engineer.
|